C-TS422-2023 SAP Practice Questions

Prepare for C-TS422-2023 with more than an answer.

208 questions in the full set20 sample questionsUpdated Aug 11, 2025
Exam fee
$1308 USD
Level
Associate
Valid for
12 months
Domains covered on the exam 11
  1. Managing Clean Core
  2. Introduction to SAP S/4HANA Supply Chain Planning
  3. Introduction to SAP S/4HANA Production Planning
  4. Demand Management in SAP S/4HANA
  5. Advanced Planning in SAP S/4HANA
  6. Capacity Planning in SAP S/4HANA
  7. Lean Manufacturing in SAP S/4HANA
  8. Master Data in SAP S/4HANA
  9. Production Orders in SAP S/4HANA
  10. Material Requirements Planning in SAP S/4HANA
  11. Process Orders in SAP S/4HANA
  1. 1

    In SAP S/4HANA Advanced Planning, what is the role of the 'Alert Monitor'?

    Show answer details

    Correct answer: C

    The Alert Monitor is a central tool for exception-based planning in PP/DS. It does not solve problems automatically but actively identifies and displays them based on a configurable alert profile. Planners use the monitor to see issues like date conflicts, capacity overloads, and pegging problems, and can often navigate directly from the alert to the relevant planning tool to resolve the issue.

  2. 2

    A planner is reviewing the capacity situation using the 'Capacity Planning Table' (CM25). They see a work center is overloaded in the current week. Which of the following are valid actions they can perform directly within this tool to level the capacity? (Select TWO)

    Show answer details

    Correct answer: A, D

  3. 3

    True or False: In a process manufacturing environment, a single Master Recipe can be used to produce multiple different finished products.

    Show answer details

    Correct answer: A

    True. A Master Recipe can be created with a 'charge quantity' and can have multiple materials assigned to it in the material-recipe assignment. This allows a single recipe, which defines the process steps, to be used for a family of similar products that follow the same production process, even if their component quantities or finished product codes differ. The specific product is determined when the process order is created.

  4. 4

    A production planner needs to perform a simulative MRP run to evaluate the impact of a potential large new sales forecast on capacity and component requirements for the next quarter, without affecting operative planning. Which tool is designed for this purpose?

    Show answer details

    Correct answer: C

    Long-Term Planning (LTP) is the standard tool used for simulative planning runs. It allows planners to create one or more inactive planning scenarios, copy demand programs (like forecasts), and run a simulative MRP. The results (simulative planned orders, capacity loads) are stored in separate planning tables and do not impact the live, operative MRP environment. This allows for what-if analysis on future demand.

  5. 5

    Case Study

    Company Background:
    AutoComponent Inc. is a Tier 1 automotive supplier that manufactures dashboards. They operate in a highly repetitive environment, producing thousands of similar dashboards per day for a major car manufacturer. Production is scheduled based on a daily run schedule quantity provided by their customer.

    Current Situation:
    To improve shop floor visibility and track work-in-process (WIP), AutoComponent wants to implement reporting points at two key stages of their production line: 'Foam Injection' (the first major step) and 'Leather Wrapping' (a later step). They need to be able to confirm the quantity of dashboards that have passed each of these points at the end of every shift. This confirmation should also trigger the backflushing of components consumed up to that point.

    Requirement:
    How must the master data and configuration be set up to enable reporting point confirmations in this repetitive manufacturing scenario?

    flowchart TD A[Start: Raw Materials] --> B{Foam Injection \n Reporting Point 1}; B --> C[Sub-Assembly Steps]; C --> D{Leather Wrapping \n Reporting Point 2}; D --> E[Final Assembly]; E --> F[End: Finished Dashboard];

    Show answer details

    Correct answer: B

    This is the correct and complete setup. The core of reporting point functionality lies in the rate routing. The specific operations that serve as reporting points must be assigned a control key that is configured for milestone/reporting point confirmation. This tells the system that quantities will be confirmed at these steps. The Repetitive Manufacturing Profile assigned to the material must also be configured to allow for reporting point backflushing, which controls the posting of activities and goods issues.

  6. 6

    A manufacturing company is implementing Production Planning and Detailed Scheduling (PP/DS) in SAP S/4HANA. They require that high-priority customer orders automatically preempt production capacity from lower-priority planned orders during the nightly planning run. Which combination of PP/DS tool and configuration is best suited to achieve this dynamic reprioritization?

    Show answer details

    Correct answer: B

    The most efficient way to handle this requirement is by using a planning heuristic combined with a correctly configured strategy profile. The strategy profile allows you to define priorities for different demand categories (like sales orders vs. forecasts). Setting 'Sales Order' as the top priority and enabling the 'Insert operations' or 'Reschedule operations' setting ensures the heuristic will automatically de-allocate and reschedule capacity from lower-priority orders to fulfill high-priority demands. The optimizer could also work but is more complex to set up and computationally intensive for a standard nightly run. A background MRP Live run and fixing pegging relationships are related but do not directly address the automatic preemption of capacity.

  7. 7

    A medical device manufacturer uses date effectivity via change numbers to manage engineering updates to their product BOMs. A new regulation requires a specific component to be replaced starting from a future production date. When a planner creates a production order with a start date after the change number's 'valid from' date, the system still selects the old component. What is the most likely reason for this issue?

    Show answer details

    Correct answer: C

    Even if the change number is correctly configured, the production version itself plays a key role. If the production version selected for the order has a validity that starts before the change number's effectivity and is not set up to be sensitive to engineering change management, the system may use the BOM structure that was valid when the production version was created or last maintained. To resolve this, the existing production version might need to be updated with a new validity period or a new production version created that is valid from the change number's effective date.

  8. 8

    A company is implementing Lean Manufacturing and wants to use KANBAN for replenishing components in a production supply area (PSA). They need to ensure that the KANBAN quantity automatically adjusts based on fluctuations in daily demand and changes in the component's replenishment lead time. Which KANBAN procedure should be configured?

    Show answer details

    Correct answer: D

    The automatic KANBAN calculation based on dependent requirements is specifically designed for this purpose. The system analyzes the dependent requirements (generated by MRP from planned/production orders for finished goods) within a specified evaluation period. It then proposes the number of KANBANs and the KANBAN quantity needed to cover that demand, considering the replenishment lead time and a safety factor. This allows the KANBAN loop to be self-adjusting to actual demand fluctuations.

  9. 9

    During a production order confirmation using a Fiori app, a user reports that component backflushing failed. An analysis in the 'Reprocess Goods Movements' (COGI) transaction shows a deficit of stock in the specified production storage location. Investigation reveals that sufficient unrestricted-use stock is available in a central warehouse storage location within the same plant. Which configuration elements must be in place to allow the system to automatically consume the stock from the central warehouse during confirmation? (Select THREE)

    Show answer details

    Correct answer: A, C, D

  10. 10

    A planner is using the MRP Live (MD01n) transaction in SAP S/4HANA. They need to run regenerative planning for a specific set of materials that are managed by a single MRP controller, without affecting other materials. Which parameters should they use?

    Show answer details

    Correct answer: C

    Regenerative planning is achieved by using Planning Mode '3 - Delete and Recreate Planning Data', which re-explodes the BOM and routings for all selected materials. To limit the scope of the run to materials managed by a specific MRP controller, a filter must be applied in the 'Material Scope' section of the MRP Live parameters. This ensures only the intended materials are planned.