PK0-005 Practice Questions
Prepare for PK0-005 with more than an answer.
Unlock the full exam and previous versions
- v1Version 1 235 questions Current
- PK0-004Legacy CompTIA Project+ (v4) 499 questions Locked
- Exam fee
- $358 USD
- Level
- Entry-level to Intermediate
- Valid for
- Lifetime (Good for Life)
Domains covered on the exam 4
- Project Management Concepts33%
- Project Life Cycle Phases30%
- Tools and Documentation19%
- Basics of IT and Governance18%
- 1
A project manager calculates the Earned Value (EV) metrics for a project and finds the Schedule Performance Index (SPI) is 0.85 and the Cost Performance Index (CPI) is 1.10. What does this indicate about the project status?
Show answer details
Correct answer: A
SPI 1.0 indicates the project is under budget (1.10), meaning for every $1 spent, $1.10 of value is earned.
- 2
The following PowerShell command is used to create a new resource group in Azure as part of a project automation script:
New-AzResourceGroup -Name 'ProjectAlphaRG' -Location '______'Which value represents a valid Azure region format to fill the blank?
Show answer details
Correct answer: A
Azure location parameters typically use the short name format without spaces, such as 'EastUS', 'WestEurope', or 'CentralUS'.
- 3
Which of the following documents is created during the Project Initiation phase and formally authorizes the project manager to apply organizational resources to project activities?
Show answer details
Correct answer: A
The Project Charter is the document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
- 4
A project manager is working with a distributed team across three time zones. The team finds that email threads are becoming unmanageable for tracking decision history. Which tool would BEST improve asynchronous collaboration and preserve decision context?
Show answer details
Correct answer: A
A Wiki/Knowledge Base allows for structured documentation, threaded comments on specific content, and version history. It is ideal for preserving the 'why' behind decisions in a way that email cannot.
- 5
In a matrix organization, a project manager is struggling to get commitment from a key technical resource who is also assigned to operational support tickets. The resource manager keeps pulling the engineer away for 'urgent' issues. Which conflict resolution technique should the project manager use FIRST to address this structural issue?
Show answer details
Correct answer: A
In a matrix organization, resources are shared. The PM must negotiate with functional managers to secure clear resource allocation. Collaborative problem solving (negotiation) is generally the best first step.
- 6
A project manager is identifying risks for a new e-commerce platform. Which of the following is considered an 'Internal' risk?
Show answer details
Correct answer: A
Staff turnover is an internal risk because it originates from within the organization and the project team.
- 7
Which diagram BEST illustrates the dependencies between project activities and is used to calculate the Critical Path?
graph LR Start((Start)) --> A[Task A: 5d] Start --> B[Task B: 3d] A --> C[Task C: 4d] B --> C C --> End((End))Show answer details
Correct answer: A
A Network Diagram (or Logic Network) visually displays the sequence of activities and their dependencies. It is the primary tool used to perform Critical Path Method (CPM) calculations to determine the shortest possible project duration.
- 8
A project manager is leading a software project using the Scrum framework. The team is midway through a sprint when a critical bug is discovered in the production system. The Product Owner asks the team to fix it immediately. How should the team handle this request?
Show answer details
Correct answer: A
In Scrum, the Sprint Backlog is generally fixed. However, for critical production issues, the team can negotiate with the Product Owner to swap work of equal size to maintain the Sprint Goal without increasing the total workload.
- 9
True or False: In a project utilizing a RACI matrix, it is recommended to have multiple people assigned as 'Accountable' (A) for a single task to ensuring shared ownership.
Show answer details
Correct answer: B
False. A fundamental rule of RACI is that there should be only ONE 'Accountable' person per task to ensure clear decision-making authority and prevent confusion about who has the final say.
- 10
A project manager is overseeing a software implementation project in a Balanced Matrix organization. A critical developer, who is also assigned to operational maintenance, has stopped attending project stand-ups due to a 'critical server outage' reported by their functional manager. The project deadline is in two weeks. Which action should the project manager take FIRST to resolve this resource conflict?
Show answer details
Correct answer: B
In a Balanced Matrix, power is shared between the Project Manager and Functional Manager. The first step is to negotiate and collaborate with the functional manager to find a solution that addresses both the operational emergency and the project deadline. Escalation is a last resort.
- 11
A PM is responsible for implementing a new customer relationship management system and has learned that the sales organization is reluctant to utilize the new system. The organization’s reluctance could jeopardize the success of the project. Which of the following steps should be taken to understand the adoption issues and gain organizational acceptance of the initiative? (Choose two.)
Show answer details
Correct answer: A
- 12
Following a successful release, a project manager sent a survey to all stakeholders to gain an understanding of opportunity areas for the team. Which of the following can use the survey results as an input?
Show answer details
Correct answer: C