PRINCE2 Agile Foundation Practice Questions

Prepare for PRINCE2-Agile-Foundation with more than an answer.

201 questions in the full set20 sample questionsUpdated Oct 25, 2025
Exam fee
$245 USD
Level
Foundation
Valid for
3 years
Domains covered on the exam 5
  1. Understand key concepts relating to projects and PRINCE212%
  2. Understand key concepts relating to projects and PRINCE2 Agile10%
  3. Understand how PRINCE2 principles, themes, processes and management products are tailored and/or applied in an agile context48%
  4. Understand the agile ways of working, key terms and techniques20%
  5. Understand the focus areas in an agile context10%
  1. 1

    Case Study

    A healthcare organization, HealthFirst, has initiated a project to develop a new patient portal. The primary goal is to allow patients to book appointments and view test results online. The project is governed by PRINCE2 Agile. The Project Board has insisted on a high level of quality due to the sensitive nature of patient data, and they have set a firm budget.

    The project is divided into three stages. Stage 1 successfully delivered the core login and security features. At the start of Stage 2, the Senior User presented a large number of new feature requests based on early feedback from a pilot group. The Project Manager is concerned that delivering all these new features will exceed the stage's time and cost tolerances, even though the overall project budget is still intact.

    The delivery team uses Scrum and works in two-week sprints. They have a stable velocity. The Project Manager needs to report the situation to the Project Board and recommend a course of action.

    Which action is the MOST appropriate application of PRINCE2 Agile principles for the Project Manager to take?

    Show answer details

    Correct answer: D

    This is a classic 'Manage by Exception' scenario. The Project Manager has forecasted that stage tolerances will be exceeded. The correct PRINCE2 action is to create an Exception Report to inform the Project Board. This report should not just state the problem but also provide options. In an agile context, the most common options are to use the flexibility of scope (by de-scoping less important features using a method like MoSCoW) or to request a change to the stage's time/cost tolerances, allowing the board to make an informed decision. This respects PRINCE2 governance while embracing agile's responsiveness to change.

  2. 2

    What is the purpose of a 'Retrospective' in an agile context?

    Show answer details

    Correct answer: C

    A retrospective is a meeting held at the end of an iteration where the team reflects on what went well, what didn't, and why. The goal is to identify and agree on specific actions to improve processes, tools, or relationships for the next iteration. This directly supports the PRINCE2 principle of 'Learn from experience'.

  3. 3

    The 'Directing a Project' process is performed by the Project Board. How is this process typically adapted in a PRINCE2 Agile project to support agile delivery teams?

    Show answer details

    Correct answer: C

    The Project Board's role remains one of governance, not day-to-day management. In an agile context, they adapt by empowering the Project Manager and delivery teams within clearly defined tolerances (fix and flex). Their involvement is crucial at key decision points, such as authorizing stages ('Managing a Stage Boundary'), but they should avoid interfering with the team's self-organization during a stage. They maintain control through Highlight Reports and Exception Reports.

  4. 4

    What is the primary purpose of the 'Project Product Description' in a PRINCE2 Agile project?

    Show answer details

    Correct answer: B

    The Project Product Description (PPD) defines what the project must deliver to be accepted. In an agile context, it's crucial for setting the overall vision and boundaries, even when the detailed features are expected to emerge. It outlines the customer's quality expectations and the acceptance criteria for the final, complete product. This provides a guiding star for the iterative development and prevents the project from drifting away from its core purpose.

  5. 5

    A project team is using T-shirt sizing (S, M, L, XL) for initial estimation of epics. What is the main advantage of this technique in the early stages of a project?

    Show answer details

    Correct answer: B

    T-shirt sizing is a form of relative estimation used for large or poorly understood work items like epics. Its main advantage is speed and simplicity. It helps teams and stakeholders quickly agree on the relative magnitude of work (e.g., 'this epic is much larger than that one') without the false precision of estimating in hours or days, which would be impossible and wasteful at such an early stage.

  6. 6

    A project is developing a new mobile banking application. The Project Board has mandated a fixed delivery date to coincide with a major marketing campaign. However, the full scope of features is still being refined with user focus groups. To align with PRINCE2 Agile principles, how should the Project Manager BEST configure the project's performance targets?

    Show answer details

    Correct answer: C

    In PRINCE2 Agile, it is fundamental to protect the level of quality. The scenario explicitly states a fixed delivery date, so time must also be fixed. To accommodate emergent requirements and stay within the fixed time and quality constraints, scope and cost are the targets that should be flexed. This allows for prioritization of features (scope) and potential adjustments to resources (cost) while ensuring a timely, high-quality delivery.

  7. 7

    During a daily stand-up, a developer mentions they need to investigate a new third-party API to determine if it's feasible for an upcoming feature. This investigation requires two days of work but will not result in a deliverable feature. In agile terminology, what is this work item BEST described as?

    Show answer details

    Correct answer: B

    A Spike is a type of user story or task aimed at answering a question or gathering information, rather than producing a shippable feature. It's used to explore a technical approach, understand a requirement better, or estimate a large, uncertain piece of work. The developer's investigation perfectly fits this definition.

  8. 8

    A Project Manager is setting up a project that will deliver a new CRM system for a highly regulated financial services company. The project must adhere to strict data security and compliance standards. According to PRINCE2 Agile guidance, which THREE of the five targets should be 'fixed' as a baseline for this project? (Select THREE)

    Show answer details

    Correct answer: A, B, C

  9. 9

    A project manager is assessing the suitability of an agile approach for an upcoming project using the Agilometer. The assessment reveals low scores for 'rich communication' and 'collaborative culture'. Based on the Agilometer results shown below, which area represents the most significant risk to the project's success if an agile approach is adopted without intervention?

    quadrantChart title Agilometer Risk Assessment x-axis Low Priority --> High Priority y-axis Low Risk --> High Risk quadrant-1 "Monitor" quadrant-2 "Action Required" quadrant-3 "Low Concern" quadrant-4 "Address if Possible" "Rich Communication": [0.8, 0.9] "Collaborative Culture": [0.7, 0.8] "Easy to Release": [0.3, 0.4] "Supportive Environment": [0.5, 0.6]

    Show answer details

    Correct answer: C

    The quadrant chart places 'Rich Communication' in the top-right quadrant, labeled 'Action Required', indicating it is both high priority and high risk. Agile methods rely heavily on effective and frequent communication. A low score in this area is a major impediment and represents the most significant risk that must be addressed for the project to succeed using agile.

  10. 10

    True or False: In a PRINCE2 Agile project, the 'Manage by Exception' principle is made redundant by the use of daily stand-up meetings and frequent releases.

    Show answer details

    Correct answer: B

    This statement is false. The 'Manage by Exception' principle is complemented, not replaced, by agile practices. Daily stand-ups and burn charts provide early warnings of potential tolerance deviations at the team level. However, the formal mechanism of escalating exceptions to the next level of management (e.g., from Project Manager to Project Board) when stage tolerances are forecast to be exceeded remains a core PRINCE2 control.