AD0-E911 Adobe Workfront Project Manager Certified Professional Practice Questions

Prepare for AD0-E911 with more than an answer.

100 questions in the full set12 sample questionsUpdated Mar 12, 2026
Exam fee
$125 USD
Time limit
100 minutes
Questions on the exam
70
Passing score
45/70 (approximately 64%)
Level
Professional
Valid for
2 years
Domains covered on the exam 3
  1. Intake and Planning30%
  2. Execute50%
  3. Closeout20%
  1. 1

    To ensure users provide all necessary information when submitting a request, a system administrator needs to prompt them with specific questions before the request is finalized. What must be attached to the Request Queue to enable this?

    Show answer details

    Correct answer: D

    Attaching a Custom Form to a Queue Topic ensures that when a user selects that topic during the request intake process, they are presented with specific custom fields to fill out.

  2. 2

    A project manager is configuring a dependency between Task A and Task B. Task B cannot start until 3 days after Task A finishes to allow for paint to dry. How should this be configured in the task settings?

    Show answer details

    Correct answer: C

    Lag time is used to create a mandatory delay between dependent tasks. A Finish-to-Start dependency with 3 days of lag ensures Task B will not begin until 3 days after Task A is completed.

  3. 3

    A user complains they cannot edit a custom form on a project, despite having 'Manage' sharing permissions on the specific project object. Upon investigation, the administrator discovers the user's global Access Level prohibits editing custom forms. What is the result of this conflict?

    Show answer details

    Correct answer: D

    In Workfront, Access Levels define what a user CAN do globally, while Sharing Permissions define what a user is ALLOWED to do on a specific object. The more restrictive setting always wins. If an Access Level denies an action, no amount of object sharing can grant it.

  4. 4

    A project manager wants to receive an immediate alert inside the Adobe Workfront interface whenever a new request is submitted to their team's request queue, but they do not want to receive an email for every request to avoid inbox clutter. How should this be configured?

    Show answer details

    Correct answer: B

    In Workfront, notification preferences are managed at the individual user level within their profile settings. Users can independently toggle Email and In-app notifications for various event triggers without affecting the rest of the team.

  5. 5

    The IT department uses a single Request Queue for all incoming tickets. They want requests to automatically assign to either the 'Hardware Support' team or the 'Software Support' team based on a drop-down field selection made by the requester on a custom form. Which Workfront feature achieves this?

    Show answer details

    Correct answer: C

    Routing Rules in Workfront evaluate custom data (like a drop-down selection on a custom form) and automatically route the request to a specific user, job role, or team based on those field values.

  6. 6

    Which TWO statements are true regarding inherited permissions in Workfront's object sharing model? (Select TWO)

    Show answer details

    Correct answer: B, C

    Because the permission is inherited from the parent, you cannot simply delete it from the child object. You must break the inheritance by removing the user's access at the parent level.

    In Workfront, permissions are inherited top-down. If a user is granted View access to a project, they inherently gain View access to the tasks and issues within that project.