Skip to content

TM12 Practice Questions

Prepare for TM12 with more than an answer.

65 questions in the full set12 sample questionsUpdated Dec 21, 2021
Exam fee
$275 USD
Time limit
180 minutes
Questions on the exam
65
Passing score
65% (scale 0-100)
Level
Advanced
Valid for
Lifetime
Domains covered on the exam 5
  1. Testing Process25%
  2. Test Management35%
  3. Defect Management15%
  4. Test Tools and Automation15%
  5. Industry-Specific Testing10%
  1. 1

    You are not confident with the assessment of the risk level and you suspect that it will be possible to find high-priority bugs in low-risk areas. Furthermore the period for test execution is very short. Your goal is to test all the product risks in a risk-based way, while assuring that each product risk gets at least some amount of testing.

    Which of the following answers describes the best test execution schedule in this scenario?

    Question exhibit
    Show answer details

    Correct answer: B

    B

  2. 2

    Test Management

    Consider an agile team adopting Extreme Programming (XP) with five developers and one tester without any coding experience.

    To which of the following activities would you expect the tester will contribute most?

    Show answer details

    Correct answer: D

    D

  3. 3

    Test Management

    Assume you have some data related to confirmation testing during system testing of a past project.
    In that project 240 bug reports have been opened once, 80 were opened twice, 10 were opened three times and no bug reports have been opened more than three times.

    You estimate that a bug report, which has failed its confirmation test, costs, on average, 3 person-hours.

    Which of the following statements correctly describe the value of these confirmatory testing activities based on cost of quality?

    Show answer details

    Correct answer: A

    A

  4. 4

    Test Tools and Automation

    Assume you are a Test Manager involved in system testing of a CRM application for a Pay-TV company. Currently the application is able to support a proper number of users assuring the required responsiveness. Since the business is expected to grow, you have been asked to evaluate the ability of the application to grow to support more users while maintaining the same responsiveness.

    Which of the following tools would you expect to be the most useful at performing this evaluation?

    Show answer details

    Correct answer: D

    D

  5. 5

    Test Management

    You are managing the system testing for a SOA based system. The integrated system consists of several subsystems:

    • a SOA middleware
    • a CRM (Customer Relationship Management) system
    • a BRM (Billing and Revenue Management) system
    • a SMS (Subscriber Management System) system
      and you performed a risk analysis based on these subsystems.

    At the end of the scheduled period for test execution you produce a first classical report based on the traditional metrics of testing. Test pass/fail status and bug status (open/resolved) That table provides you a distorted picture of the quality risk, because there is no indication of the risk level of the failed tests, the tests not run, or the open bugs. Thus, you produce the following table to solve this distortion issue:

    In the table above, where you have introduced the concept of risk weighting, the highest risk test or bug report has a score of 1, while the lowest risk test or bug report has a score of 0.04.

    Which of the following subsystems, based on the risk scores of the table, is most risky?

    Question exhibit
    Show answer details

    Correct answer: B

    B

  6. 6

    Test Management

    Which of the following statements best describes an appropriate approach for managing exploratory testing?

    Show answer details

    Correct answer: B

    B

Create an account to continue.