  1. 1

    What is the recommended timebox for a Daily Scrum event, regardless of the length of the Sprint?

    Show answer details

    Correct answer: B

    The Scrum Guide prescribes a strict timebox of 15 minutes for the Daily Scrum. This fixed duration encourages a concise and focused discussion and prevents it from turning into a long status or problem-solving meeting. The timebox remains the same whether the Sprint is one week or four weeks long.

  2. 2

    A Product Owner is refining the Product Backlog and wants to ensure the user stories are well-formed. They are using the INVEST acronym as a guide. According to the INVEST model for user stories, which of the following characteristics are essential? (Select THREE)

    Show answer details

    Correct answer: A, C, E

    Stories should be self-contained to avoid dependencies.

    Stories are not contracts; details can be negotiated between the PO and Developers.

    The story should be small enough to be completed in a Sprint.

  3. 3

    A client wants to hire a software development agency to build a new product using Scrum. The client is concerned about budget overruns and wants a predictable cost, but the agency is concerned about fixed scope in an agile environment. Which type of contract would best suit this situation, balancing the client's need for budget control with the agency's need for flexibility?

    Show answer details

    Correct answer: C

    A Graduated Time and Materials contract can be an effective agile contract. It involves a variable hourly rate that changes based on performance (e.g., the rate decreases if the project is late or increases if it's early), creating a shared risk and reward model. This provides budget incentives for the agency while allowing the scope flexibility inherent in Scrum.

  4. 4

    A retail company, 'FashionFast,' is using Scrum to develop its e-commerce platform. The team has a new Scrum Master who observes the Daily Scrum. The meeting consistently takes 30-40 minutes. Each Developer gives a detailed report of what they did yesterday and what they will do today directly to the Scrum Master. There is little interaction between Developers, and problem-solving discussions often derail the meeting. After the meeting, Developers frequently approach the Scrum Master individually to report impediments.

    The Scrum Master recognizes that the Daily Scrum is being run as a traditional status meeting. The primary goal of improving team collaboration and creating a daily plan is being missed. The Scrum Master wants to coach the team to run the event more effectively according to Scrum principles.

    What is the most effective initial step the Scrum Master should take to improve the Daily Scrum?

    Show answer details

    Correct answer: B

    The core problem is the format and purpose of the meeting, not just its length. The most effective coaching action is to address the behavior directly by restructuring the meeting's focus. The Scrum Master should coach the Developers to collaborate as a self-managing team, focusing their discussion on how they can work together to achieve the Sprint Goal. This addresses the root cause of the meeting being a status report to a manager.

  5. 5

    A team needs to estimate a large Product Backlog with over 100 items for the first time to get a rough idea for a release plan. A detailed Planning Poker session for every item would be too time-consuming. Which estimation technique is most suitable for quickly getting a relative size estimate for a large number of items?

    Show answer details

    Correct answer: B

    Affinity Estimation (or Affinity Mapping) is a technique used to quickly and collaboratively estimate a large number of user stories. Team members place items on a wall or board under different size categories (e.g., T-shirt sizes like S, M, L, XL). This visual and collaborative method is much faster for high-level estimation than discussing each item individually as in Planning Poker.

  6. 6

    During Sprint Planning, the team selects several high-priority Product Backlog Items. What is the primary purpose of crafting a Sprint Goal after selecting these items?

    Show answer details

    Correct answer: B

    The Sprint Goal provides coherence and focus for the Sprint, encouraging the Developers to work together. It is an objective that the team commits to, but it also provides flexibility. If the work turns out to be different than expected, the Developers can collaborate and adapt their plan to still achieve the Sprint Goal, even if it means not completing every single forecasted Product Backlog Item.

  7. 7

    A Scrum Team wants to visualize not only their progress within the Sprint but also any scope changes that occur, such as work being added or removed from the Sprint Backlog. Which information radiator is better suited than a simple Burn-down chart for visualizing both work completion and scope changes over time?

    Show answer details

    Correct answer: B

    A Burn-up chart tracks progress toward a goal while also visualizing scope. It has two lines: one showing the total scope of work and another showing the work completed. If new items are added, the scope line goes up, making scope changes clearly visible. A simple Burn-down chart only shows work remaining and can be misleading if scope is added.

    xychart-beta title "Sprint Burn-up Chart" x-axis "Days in Sprint" [0, 10] y-axis "Story Points" [0, 120] line "Total Scope" [[0, 100], [3, 100], [4, 115], [10, 115]] line "Completed Work" [[0, 0], [1, 10], [2, 22], [3, 35], [4, 50], [5, 60], [6, 75], [7, 85], [8, 95], [9, 105], [10, 115]]

  8. 8

    A new Scrum team is being formed within a marketing agency. The management wants to assign the role of Product Owner to someone who can best ensure the product delivers maximum business value to their clients.

    Show answer details

    Correct answer: B

    The Scrum Guide explicitly states that the Product Owner is accountable for maximizing the value of the product resulting from the work of the Scrum Team. The Scrum Master is a servant-leader responsible for facilitation and impediment removal. The Developers are accountable for the technical solution, and the entire Scrum Team is self-managing.

  9. 9

    A project team is transitioning from a traditional Waterfall methodology to an Agile approach. They are studying the Agile Manifesto to guide their new way of working.

    Show answer details

    Correct answer: D

    The Agile Manifesto states four core values. One of these is valuing 'Responding to change over following a plan.' While 'Individuals and interactions' is also a value, it is paired with 'processes and tools.' 'Comprehensive documentation' and 'Contract negotiation' are the items that are valued less than their counterparts (working software and customer collaboration, respectively).

  10. 10

    A team is discussing the nature of story points during their first estimation session.

    True or False: A story point is a universal unit of measure that directly translates to a specific number of hours and should be consistent across different Scrum teams.

    Show answer details

    Correct answer: B

    False. Story points are a relative unit of measure, unique to each team. They represent a combination of effort, complexity, and uncertainty, and do not directly correlate to a fixed number of hours. Their value is specific to the team that made the estimate and should not be compared between teams.