MB-335 Dynamics 365 Supply Chain Management Expert Practice Questions
Prepare for MB-335 with more than an answer.
- Exam fee
- $165 USD
- Level
- Expert
Domains covered on the exam 5
- Configure products22.5%
- Configure production prerequisites22.5%
- Implement production methods22.5%
- Configure and manage production control17.5%
- Implement additional supply chain management features12.5%
- 1
You are creating a costing version for the upcoming fiscal year to update the standard costs of manufactured goods. After running BOM calculations, you need to ensure these new costs are used for all inventory transactions. What is the final step required to make the calculated costs in the costing version active?
Show answer details
Correct answer: B
After costs are calculated and stored in a costing version as pending prices, they are not yet live. The final, critical step is to activate these pending prices. The activation process updates the active standard cost for the items, which will then be used for inventory valuation and transaction costing.
- 2
A chemical company must comply with regulations that restrict the sale of certain products to specific countries. They also need to print a Safety Data Sheet (SDS) automatically when shipping any order containing a hazardous item. Which feature should be used to manage these compliance rules?
Show answer details
Correct answer: B
The Product compliance feature is designed specifically for these requirements. It allows you to configure regulated products, set up restrictions on where they can be sold, and manage required documentation like Safety Data Sheets (SDS) that need to be provided with shipments.
- 3
True or False: In a lean manufacturing environment, a production flow model must be approved and activated before it can be used in a kanban rule.
Show answer details
Correct answer: A
This is true. Similar to BOMs and routes, production flows use a versioning system. A specific version of a production flow must be approved and then activated to make it available for use in active kanban rules and for processing kanban jobs.
- 4
A consultant is configuring the warehouse processes for production. When raw materials are needed for a production order, a warehouse worker must be directed to pick the items from bulk storage and move them to a specific staging location next to the production line. Which warehouse management feature is used to define this pick-and-put logic?
Show answer details
Correct answer: B
Work templates define the sequence of operations (e.g., 'Pick' then 'Put'). Location directives are the rules that determine the specific locations for those operations. For raw material picking, you would configure a location directive to find the item in bulk storage for the 'Pick' step and another location directive to find the production input location for the 'Put' step.
- 5
A company manufactures a product that requires two operations, Assembly (Op 20) and Testing (Op 30), to run in parallel. After both are complete, a final Packaging operation (Op 40) begins. The process starts with a Kitting operation (Op 10).
How should the
Next operation numberbe configured on the route to model this parallel execution?flowchart TD A[Op 10: Kitting] --> B{Op 20: Assembly}; A --> C{Op 30: Testing}; B --> D[Op 40: Packaging]; C --> D;Show answer details
Correct answer: D
To create parallel operations, you define one path sequentially (e.g., Op 10 -> Op 20 -> Op 40). Then you create the parallel operation (Op 30) and use the route network graphical view to manually draw the dependencies, making Op 10 a predecessor to Op 30, and Op 30 a predecessor to Op 40. This creates the fork/join structure required for parallel execution.
- 6
A food processing company uses Dynamics 365 Supply Chain Management and manufactures yogurt. The active culture (a key ingredient) has a variable potency that affects the required quantity in each batch order. The company needs to adjust the quantity of the active culture based on its batch attribute for 'potency percentage' to ensure a consistent final product. Which feature should be configured to automate this ingredient quantity adjustment?
Show answer details
Correct answer: B
Batch balancing is the correct feature for process manufacturing scenarios where ingredient quantities need to be adjusted based on the concentration or potency of active components. By defining the active ingredient and its base attribute (potency), the system can automatically recalculate the required quantity of that ingredient in a batch order to meet the formula's specifications.
- 7
A manufacturing firm is implementing Engineering Change Management. They need to establish a formal review process for all proposed changes to their core products. The process requires that a cross-functional team, including members from engineering, production, and quality assurance, must approve a change before it can be converted into an engineering change order. Which TWO components are essential to configure this approval workflow? (Select TWO)
Show answer details
Correct answer: B, E
A workflow must be configured and assigned to the engineering change request to manage the approval steps, user assignments, and conditions for the review process.
User groups are necessary to assign approval tasks to the correct cross-functional teams (engineering, production, etc.) within the workflow definition.
- 8
A company produces industrial machinery and subcontracts the powder coating operation for the machine's chassis. The company ships the raw steel chassis to the vendor, who then applies the coating and ships it back. To manage this, a functional consultant creates a route operation for the subcontracted work and links it to a service item. How should the bill of materials (BOM) for the finished machinery be configured to ensure the raw steel chassis is consumed from the company's inventory when it is shipped to the subcontractor?
Show answer details
Correct answer: B
To consume company-owned inventory for a subcontracted operation, the component (the raw chassis) must be added as a standard BOM line of type 'Item'. Then, this BOM line must be linked to the specific operation number of the subcontracting step in the route. This ensures the material is picked and issued for that operation, which triggers the transfer to the subcontractor.
- 9
A company is configuring Planning Optimization for its multi-site operations. To improve performance, they want to ensure that the planning run for their European sites only considers demand and supply within Europe, while a separate run handles North America. Which configuration is most critical for segregating the planning runs by region?
Show answer details
Correct answer: D
In Planning Optimization, the scope of a planning run is defined by the batch job that executes it. To segregate runs by region, you must create separate batch jobs (or recurrences) and apply filters to each. These filters can specify which legal entities or sites should be included, effectively creating distinct planning boundaries for Europe and North America.
- 10
A plastics manufacturer uses a resource group of three identical injection molding machines. To optimize scheduling, they need to ensure that production jobs can be scheduled on any of the three machines based on availability. However, certain complex molds require a specific machine that has been upgraded with higher pressure capabilities. What should be configured on the resources and routes to support this requirement?
Show answer details
Correct answer: B
Capabilities are used to match operational requirements with resource abilities. By defining a common 'Standard' capability, most jobs can run on any machine. By adding a specific 'HighPressure' capability to only the upgraded machine and setting this as a requirement on the route operations for complex molds, the scheduler will correctly assign those jobs only to the capable resource, while standard jobs can be load-balanced across all three.