  1. 1

    During a Sprint Retrospective, the team identifies that conflicting priorities from different stakeholders are causing them to constantly shift focus, endangering the Sprint Goal. Which of the following are productive actions for the Scrum Master to take? (Select TWO).

    Show answer details

    Correct answer: B, D

    This is a key service the Scrum Master provides to the Product Owner. Helping the PO develop skills to manage competing stakeholder demands ensures that a clear, unified direction is provided to the team.

    This action addresses the problem at a systemic level. By facilitating a discussion, the Scrum Master helps create transparency and establish clear communication protocols, which protects the team's focus and empowers the Product Owner.

  2. 2

    Which of the following best describes the Sprint Backlog?

    Show answer details

    Correct answer: C

    The Sprint Backlog is created by the Developers during Sprint Planning. It is a highly visible, real-time picture of the work they plan to accomplish during the Sprint to achieve the Sprint Goal. It is a living artifact that can be updated throughout the Sprint by the Developers as they learn more.

  3. 3

    Case Study:

    A healthcare tech company, HealthForward, is developing a new patient portal. They have two Scrum Teams: Team Apollo (working on the user interface) and Team Artemis (working on backend services and database). Both teams pull from the same Product Backlog managed by a single Product Owner. During Sprint 3, Team Apollo realizes they cannot complete a key feature because it depends on an API that Team Artemis has not yet built. This dependency was not identified during Sprint Planning.

    The result is that Team Apollo fails to deliver a usable feature, and the Sprint Goal is endangered. The Product Owner is frustrated because the highest-priority item in the backlog was not completed. Team Artemis explains that the API was a lower priority for them based on their understanding of the overall architecture. The situation has created tension between the teams and a lack of trust.

    As a Scrum Master coaching both teams, what is the most effective, long-term solution to prevent this from happening in future Sprints?

    Show answer details

    Correct answer: D

    This is the most effective and proactive solution. The root cause is the late discovery of the dependency. By having both teams refine the Product Backlog together, they can collaboratively identify cross-team dependencies well before a Sprint begins. This allows the Product Owner to order the backlog in a way that resolves these dependencies, or for the teams to create a plan to manage them. This approach fosters communication, transparency, and a shared understanding of the work, directly addressing the core problem.

  4. 4

    What happens to the Sprint Backlog items that are not finished by the end of the Sprint?

    Show answer details

    Correct answer: B

    At the end of a Sprint, the Sprint Backlog ceases to exist. Any incomplete Product Backlog Items are returned to the Product Backlog. The Product Owner then re-orders them based on the current priorities and understanding of value. They are not automatically carried over to the next Sprint, as their value and priority may have changed.

  5. 5

    A new Scrum Team is struggling to understand what it means for a Product Backlog Item to be 'Done'. The Developers consider it 'Done' when the code is written, but the Product Owner expects it to be tested and deployed to a staging environment. This is causing conflict in the Sprint Review. What should the Scrum Master facilitate the creation of?

    flowchart TD A[PBI Selected] --> B{Code Complete?} B -->|Yes| C{Peer Reviewed?} B -->|No| D[Continue Coding] C -->|Yes| E{Unit Tests Pass?} C -->|No| F[Revise Code] E -->|Yes| G{Integrated & Deployed?} E -->|No| H[Fix Tests] G -->|Yes| I([Done]) G -->|No| J[Resolve Integration] style I fill:#9f9,stroke:#333,stroke-width:2px

    Show answer details

    Correct answer: C

    The problem described is a classic symptom of a missing or misaligned Definition of Done (DoD). The DoD is a formal description of the state of the Increment when it meets the quality measures required for the product. It creates transparency by providing a shared understanding of what work was completed. The Scrum Master should facilitate a workshop for the entire Scrum Team to create a DoD that everyone agrees upon.

  6. 6

    The Product Owner is unavailable for a week, and the Developers need clarification on a Product Backlog Item they are working on during the Sprint. What should the Developers do?

    Show answer details

    Correct answer: C

    Scrum teams are self-managing. While the Product Owner is the final authority on the Product Backlog, the Developers are empowered to make decisions to keep moving toward the Sprint Goal. The best course of action is to use their professional judgment, document their assumptions, and proceed, ensuring they sync with the PO as soon as possible. This maintains momentum and embodies the principle of self-management.

  7. 7

    True or False: The Sprint Review is the only time during a Sprint that stakeholders are allowed to provide feedback on the product.

    Show answer details

    Correct answer: B

    This statement is false. The Sprint Review is a formal event for stakeholder feedback, but collaboration is not limited to this event. The Product Owner is expected to be in regular contact with stakeholders throughout the Sprint to gather insights and refine the Product Backlog. This ongoing collaboration helps ensure that the Sprint Review does not contain major surprises.

  8. 8

    A Scrum Team has just completed its first Sprint. During the Sprint Retrospective, the Developers express frustration that they were constantly interrupted by stakeholders asking for status updates. Which of the five Scrum Values is most directly compromised by this situation?

    Show answer details

    Correct answer: B

    The value of 'Focus' is most directly compromised. By allowing frequent interruptions, the team loses its ability to concentrate on the work of the Sprint and progress towards the Sprint Goal. The Scrum Master should coach the stakeholders on how to interact with the team appropriately, likely directing communication through the Product Owner and respecting the Sprint's boundary.

  9. 9

    True or False: The three pillars of empiricism require that the process and work must be visible to those performing the work as well as those receiving the work.

    Show answer details

    Correct answer: A

    This statement is true. It directly describes the pillar of Transparency. For inspection and adaptation to be effective, the state of the artifacts and progress towards goals must be transparent to all involved parties, ensuring everyone operates from a common understanding.

  10. 10

    A Product Owner is struggling to communicate the long-term direction for the product to the Scrum Team and stakeholders. This has resulted in Sprint Goals that feel disconnected from any larger objective. Which artifact's commitment is likely missing or poorly defined?

    Show answer details

    Correct answer: C

    The Product Goal is the commitment for the Product Backlog. It describes a future state of the product which can serve as a target for the Scrum Team to plan against. A missing or poorly defined Product Goal leads to a lack of long-term vision, causing Sprint Goals to seem random and tactical rather than strategic steps toward a larger objective.