- 1
To ensure improvements from a 5S initiative are maintained, a manager has created visual aids and checklists for daily cleaning and organization tasks. Which Lean Control methods are being applied? (Select TWO)
Show answer details
Correct answer: B, D
Using visual aids (like photos of the correct layout) and checklists are forms of Visual Controls. The checklists also serve as a tool for conducting regular 5S Audits. Both are crucial for the 'Sustain' phase of 5S to prevent the workspace from reverting to its previous state. Kanban is for inventory control, and Poka-Yoke is for error-proofing.
- 2
A project's goal is to reduce the average processing time of loan applications. The team has identified several potential input variables (X's) such as 'Applicant's Credit Score', 'Completeness of Application', and 'Loan Officer Experience'. The output variable (Y) is 'Application Processing Time'. Which tool is best suited to document and rank the potential relationships between these inputs and the output?
Show answer details
Correct answer: B
An X-Y Diagram, also known as a Cause and Effect Matrix, is a tool used to prioritize potential root causes (X's). It works by systematically evaluating the correlation between key process inputs (X's) and customer outputs (Y's). The team assigns numerical scores to these relationships, resulting in a ranked list of the most influential inputs to investigate further.
- 3
A project team at an insurance company is working to reduce errors in claims processing. After implementing several process changes, they need to document the new standard procedure and create a plan for what to do if error rates begin to increase again. Which document combines these process monitoring and response elements?
Show answer details
Correct answer: C
A Control Plan is a living document created during the Control phase that details how to maintain the gains from an improvement project. It specifies the key process variables to monitor, the methods and frequency of measurement, and, crucially, a Response Plan that outlines the specific actions to be taken if the process becomes unstable or goes out of control.
- 4
What is the primary purpose of developing a business case in the Define phase of a Lean Six Sigma project?
Show answer details
Correct answer: B
The business case provides the justification for undertaking the project. It links the project to the organization's strategic goals and explains, often in financial terms, why the project is a priority and what the expected return on investment will be. It answers the question, 'Why should we do this project?'
- 5
A process for manufacturing shafts has specification limits of 20mm ± 0.5mm (LSL=19.5, USL=20.5). After collecting data, the process is found to have a mean of 20.4mm and a standard deviation that results in a calculated Cp of 1.67 and a Cpk of 0.33. What does the significant difference between the Cp and Cpk values indicate?
graph TD subgraph "Specifications" LSL[LSL: 19.5] Target[Target: 20.0] USL[USL: 20.5] end subgraph "Process Distribution" Mean[Mean: 20.4] end LSL -- "Tolerance Width" --> USL Target -- "Process is Off-center" --> MeanShow answer details
Correct answer: A
Cp measures the potential capability of the process, assuming it is perfectly centered. A Cp of 1.67 is very good, indicating the process spread is narrow compared to the tolerance width. Cpk measures the actual capability, taking the process centering into account. A very low Cpk (0.33) combined with a high Cp indicates that while the process is consistent (low variation), its mean (20.4mm) is significantly shifted away from the target (20.0mm), causing defects.
- 6
A hospital's patient intake process is being analyzed for inefficiencies. The project team has identified that a significant amount of time is wasted due to staff members having to walk to a central supply closet to get forms. This is categorized as which of the 8 wastes?
Show answer details
Correct answer: B
The waste of Motion refers to the unnecessary movement of people (e.g., walking, bending, reaching). In this scenario, the staff members walking to get forms is a classic example of wasted motion. Transportation refers to the unnecessary movement of materials or products, not people.
- 7
A team is analyzing the causes of delays in a software bug-fixing process. They have brainstormed a list of potential causes related to people, tools, and procedures. Which tool is most effective for organizing these brainstormed ideas into logical categories to visualize potential root causes?
Show answer details
Correct answer: C
A Fishbone (or Ishikawa) Diagram is specifically designed for root cause analysis. It helps teams visually organize the potential causes of a problem (the effect) into logical categories (like Manpower, Method, Machine, etc.), which facilitates a structured brainstorming session. SIPOC defines process scope, Pareto prioritizes causes by frequency, and Control Charts monitor process stability over time.
mindmap root((Problem: Bug Fix Delays)) People Lack of Training Poor Communication Process Complex Approval No Prioritization Tools Slow System Outdated Debugger Environment Noisy Office - 8
A factory implements a Poka-Yoke device on an assembly line that physically prevents a part from being installed upside down. True or False: This is an example of a 'detection' type of Poka-Yoke.
Show answer details
Correct answer: B
This statement is false. A device that physically prevents an error from occurring is a 'prevention' or 'control' type of Poka-Yoke, which is the most effective form. A 'detection' type would allow the mistake to happen but would immediately signal an alarm or stop the line to alert the operator.
- 9
A project team is calculating the Cost of Poor Quality (COPQ) for a billing process. They discover that a significant cost is associated with the time employees spend re-issuing incorrect invoices before they are sent to the customer.
Show answer details
Correct answer: D
Internal Failure Costs are incurred to remedy defects discovered before the product or service is delivered to the customer. Since the incorrect invoices are being re-issued before being sent out, the associated costs (labor, materials) are categorized as internal failure costs. External failure costs occur after the customer receives the product.
- 10
A team has successfully improved a process and is now developing a control plan to sustain the gains. Which of the following are essential elements of a robust Control Plan? (Select THREE)
Show answer details
Correct answer: A, C, E
A robust control plan must specify what is being controlled, how it is measured (method and frequency), and what to do if it goes out of control (the reaction plan). The original project champion and the budget from a previous phase are historical data and not active components of the ongoing control plan.