PSPO-I Practice Questions
Prepare for PSPO-I with more than an answer.
- Exam fee
- $200 USD
- Level
- Foundation
- Valid for
- Lifetime - no renewal required
Domains covered on the exam 3
- Understanding and Applying the Scrum Framework25%
- Developing People and Teams10%
- Managing Products with Agility65%
- 1
A Product Owner can delegate some of their responsibilities, such as writing Product Backlog Items.
Show answer details
Correct answer: A
The Scrum Guide states, 'The Product Owner may do the above work [Product Backlog management] or may delegate the responsibility to others. Regardless, the Product Owner remains accountable.' This means that while the Product Owner can have Developers or others help with the mechanics of managing the backlog, the accountability for its content, ordering, and transparency always rests with the Product Owner.
- 2
The activity of Product Backlog refinement should ideally consume no more than what percentage of the Developers' capacity?
Show answer details
Correct answer: B
While the 2020 Scrum Guide removed the specific 10% guideline to be less prescriptive, it remains a widely accepted and effective rule of thumb in the Scrum community. It is considered a best practice to ensure the backlog is well-prepared for future Sprints without consuming excessive time from the current Sprint's development work. The PSPO exam often tests these commonly understood practices.
- 3
A Scrum Team is working in an environment where releases are tightly controlled and can only happen at the end of each quarter. How does this organizational constraint affect the work of the Product Owner and the Scrum Team?
Show answer details
Correct answer: C
A key concept in Scrum is the separation of 'releasable' from 'released'. The Scrum Team's goal is to produce a valuable and usable Increment that meets the Definition of Done every Sprint. This Increment is potentially releasable. The decision of when to actually release it is a separate business decision, which the Product Owner makes. Even with infrequent release windows, the team must continue to produce integrated, tested Increments to maintain transparency, control risk, and provide opportunities for inspection and feedback.
- 4
What is the primary purpose of the Sprint Goal?
Show answer details
Correct answer: B
The Sprint Goal is the single objective for the Sprint. It is a commitment by the Developers that provides flexibility in terms of the exact work needed to achieve it. It creates coherence and focus, encouraging the Scrum Team to work together rather than on separate initiatives. It answers the question of 'why' the Sprint is valuable, guiding the team's work and decisions throughout the Sprint.
- 5
A Product Owner is explaining the Product Backlog to stakeholders. They use the following diagram to illustrate how the backlog is structured. What does this diagram imply about the Product Backlog items?
graph TD subgraph Product_Backlog direction LR A[High Priority Item (Detailed, Small) ] --> B[Medium Priority Item (Less Detailed) ] B --> C[Low Priority Item (Large, Vague) ] endShow answer details
Correct answer: B
This illustrates a well-refined Product Backlog. Items at the top, which are candidates for the next Sprints, are well-understood, detailed, and small enough to be completed in a Sprint. Items further down the backlog represent future work and are therefore less defined, larger, and more abstract (often called 'epics'). This is a result of the ongoing activity of Product Backlog refinement.
- 6
A Product Owner is managing a mature product with a stable user base. A new competitor has just launched a disruptive feature that is gaining market traction. The stakeholders are pressuring the Product Owner to pivot the product strategy immediately to copy the competitor. What is the most effective first action for the Product Owner to take?
Show answer details
Correct answer: C
The most effective first action is based on empiricism. Before committing to a strategic pivot and significant development work, the Product Owner must validate the assumption that the competitor's feature will provide value to their specific user base. Proposing an item to research and experiment allows the team to make a data-driven decision, minimizing risk and ensuring that any future work is focused on maximizing value. Simply copying the feature is reactive and risky. Creating a new Product Goal is a good step, but it should be informed by evidence, not just competitive pressure. Canceling the current Sprint is a drastic measure and only appropriate if the Sprint Goal has become obsolete, which isn't necessarily the case yet.
- 7
During Sprint Planning, the Developers inform the Product Owner that they can't complete all the high-priority items that the Product Owner had hoped to include. The Product Owner is concerned about not meeting stakeholder expectations for the upcoming Sprint Review. What is the Product Owner's primary accountability in this situation?
Show answer details
Correct answer: B
The Developers are accountable for selecting the amount of work they can complete in a Sprint. The Product Owner respects this as part of the team's self-management. The PO's primary accountability is to maximize value. In Sprint Planning, this is achieved by collaborating with the Scrum Team to define a valuable Sprint Goal. This goal provides focus and direction, even if not all desired items are included. Pushing the team, reducing quality, or unilaterally changing priorities undermines Scrum principles and team trust.
- 8
True or False: The Product Owner is the sole person responsible for ordering the Product Backlog, but they must get approval from a stakeholder committee before making significant changes to the order.
Show answer details
Correct answer: B
According to the Scrum Guide, the Product Owner is one person, not a committee, and is solely accountable for effective Product Backlog management, which includes ordering. For Product Owners to succeed, the entire organization must respect their decisions. While they should collaborate with and consider input from stakeholders, they do not require committee approval to change the Product Backlog. This authority is essential for agility.
- 9
A Product Owner is working with multiple Scrum Teams on a single large product. Which of the following are necessary to ensure transparency and the ability to deliver an integrated Increment? (Select TWO)
Show answer details
Correct answer: B, C
- 10
Case Study: HealthFirst Mobile App
HealthFirst, a healthcare startup, is developing a mobile application to help users track their fitness and nutrition. The Product Owner, Sarah, has been with the company since its inception. The initial Product Goal is "To launch a minimum viable product (MVP) that allows users to log daily meals and exercise, providing basic calorie tracking."
After three Sprints, the Scrum Team has delivered a functional Increment that meets the MVP criteria. During the Sprint Review, key stakeholders, including the CEO and lead investor, are impressed. The CEO immediately suggests the next big feature: integrating with wearable fitness devices. The lead investor, however, wants to focus on monetization by adding a premium subscription feature for personalized meal plans.
Sarah is now faced with conflicting, high-priority requests from powerful stakeholders. The Developers have also noted significant technical debt accumulating in the logging feature, which they believe will slow down future development if not addressed soon. The Product Backlog is currently ordered with some small user-requested improvements at the top for the next Sprint.
How should Sarah, as the Product Owner, best proceed to manage the Product Backlog for the upcoming Sprints?
Show answer details
Correct answer: C
The Product Owner's core accountability is to maximize value. This requires balancing stakeholder desires, technical feasibility, and user needs. The best approach is to use data and evidence to facilitate a strategic conversation with stakeholders, rather than just following the most powerful voice. Presenting potential ROI helps frame the decision in terms of value. Simultaneously, the PO must work with the Developers to manage the health of the product by addressing technical debt. This balanced, evidence-based approach is central to effective Product Ownership.