  1. 1

    A project is being run within a formal corporate programme. How should the 'Organizing' practice be tailored to reflect this context?

    Show answer details

    Correct answer: B

    When a project is part of a programme, it does not operate in isolation. The programme will have its own governance structure. The project's organization must be designed to fit within this structure. This often means programme-level roles (like the Programme Manager) may take on some of the duties of the project's Executive, and programme-level strategies (for communication, risk, etc.) will be adopted by the project.

  2. 2

    The diagram below shows the key roles in a quality review meeting. Which role is responsible for chairing the meeting and ensuring it is conducted properly?

    Show answer details

    Correct answer: C

    The Chair is responsible for the overall conduct of the quality review meeting. They ensure that the review stays focused, all reviewers have a chance to contribute, and a clear decision is reached (complete, conditionally complete, or incomplete). This role is independent of the Producer (creator of the product) and the Reviewers.

    flowchart LR subgraph QualityReviewMeeting Producer[Producer] -- Submits Product --> Chair{Chair} Chair -- Distributes Product & Criteria --> Reviewers[Reviewers] Reviewers -- Provide Feedback --> Chair Chair -- Manages Meeting --> Outcome[Review Outcome] end
  3. 3

    What is the relationship between the Benefits Management Approach and the Business Case?

    Show answer details

    Correct answer: C

    The Business Case documents the justification for the project, including the expected benefits. The Benefits Management Approach provides the detailed plan for how those benefits will be tracked, measured, and ultimately realized, both during and after the project. It essentially describes the 'how' for the 'what' promised in the Business Case.

  4. 4

    True or False: The Project Manager is a member of the Project Board.

    Show answer details

    Correct answer: B

    False. The Project Board consists of the Executive, Senior User(s), and Senior Supplier(s). The Project Manager reports to the Project Board and is responsible for the day-to-day management of the project on their behalf, but is not a member of the board itself. This maintains a clear line of authority and accountability.

  5. 5

    A software project passes all specified quality tests, is delivered on time, and within budget. However, user adoption is extremely low, and feedback indicates the system is difficult to use. Which PRINCE2 concept was most likely poorly defined in the Project Product Description?

    Show answer details

    Correct answer: C

    This scenario describes a product that meets its technical specification but is not 'fit for purpose'. The quality criteria in the Project Product Description were likely focused on technical aspects (e.g., 'processes transactions in <2 seconds') but missed crucial non-functional, usability-focused criteria (e.g., 'a new user can complete a standard transaction with <5 minutes of training'). Effective quality criteria must cover all aspects that determine if the product will deliver the expected benefits.

  6. 6

    A small, internal IT project with a duration of six weeks is being initiated. The Project Manager suggests dispensing with management stages altogether to reduce administrative overhead. Which PRINCE2 principle is being violated by this approach?

    Show answer details

    Correct answer: C

    The 'Manage by stages' principle requires that a PRINCE2 project is planned, monitored, and controlled on a stage-by-stage basis. Even for a short project, there must be at least two stages: the initiation stage and at least one management stage. This provides the Project Board with control points to assess viability. Tailoring would involve having very few, short stages, not eliminating them entirely.

  7. 7

    According to the 'People' element introduced in PRINCE2 7, what is a primary responsibility of the Project Manager regarding the project team?

    Show answer details

    Correct answer: B

    The 'People' element in PRINCE2 7 emphasizes that successful projects are delivered by people, not just through processes. A key role of the Project Manager is to lead and support the team by creating a positive and collaborative culture, managing relationships, and ensuring effective communication.

  8. 8

    A project is underway to develop a new CRM system. The sales department (Senior User) is advocating for additional features, claiming they are essential. The finance department (providing funding) argues these features are 'gold plating' and will push the project over budget, threatening the Business Case. The conflict is causing delays and team morale is dropping.

    As the Project Manager, which course of action best aligns with PRINCE2 principles and practices?

    Show answer details

    Correct answer: D

    This is the correct PRINCE2 approach. The conflict represents an 'issue', specifically a 'Request for Change'. The Project Manager should not make a unilateral decision. Instead, they must use the formal issue and change control procedure to assess the impact of the change on all project constraints and the Business Case. This provides the Project Board (Change Authority) with the necessary information to make an informed decision, thereby resolving the conflict through a defined process.

  9. 9

    A project's key technology becomes obsolete due to a sudden market innovation, rendering the expected benefits unachievable. However, the corporate sponsor insists the project must be completed for strategic reasons. Which TWO PRINCE2 principles are most directly in conflict in this situation? (Select TWO).

    Show answer details

    Correct answer: B, D

    The 'Continued business justification' principle is at risk because the original benefits are no longer achievable, making the Business Case invalid.

    The 'Define roles, responsibilities, and relationships' principle is also in conflict. The corporate sponsor is acting outside the defined governance structure by insisting the project continue without a valid Business Case, undermining the authority and responsibility of the Project Board to stop a non-viable project.

  10. 10

    What is the primary characteristic that distinguishes a PRINCE2 'product' from a simple 'deliverable' or 'task output'?

    Show answer details

    Correct answer: C

    A PRINCE2 product (which can be a management or specialist product) is defined with a detailed Product Description. This description includes its purpose, composition, derivation, format, and, crucially, the quality criteria against which it will be assessed. A simple 'deliverable' may not have this level of formal definition and quality specification.