  1. 1

    A project encountered a problem and reached a milestone.

    In which of the following documents will the stakeholders MOST likely find information on these events?

    Show answer details

    Correct answer: B

    B

  2. 2

    A project manager has taken over a project that is already in progress. The project manager notices the functional manager of one team is unaware of the current progress.

    Which of the following should the project manager do? (Choose two.)

    Show answer details

    Correct answer: B, D

    B,D

    B,D

  3. 3

    A team member has reported Task 3 will be completed ahead of schedule.

    Using the given chart, which of the following represents the critical path if Task 3 is completed in two days?

    Question exhibit
    Show answer details

    Correct answer: A

    A

  4. 4

    A project manager is working on the project charter.

    Which of the following phases does this describe?

    Show answer details

    Correct answer: C

    C--Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 107

  5. 5

    A project manager is unsure if the quality of a deliverable from a SME meets specifications.

    Which of the following is the BEST way for the project manager to address the issue?

    Show answer details

    Correct answer: D

    D--Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 261

  6. 6

    A project manager is attempting to establish the proper sequencing and duration of project activities.

    Which of the following would be the MOST beneficial?

    Show answer details

    Correct answer: C

    A--Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 160

  7. 7

    The quarterly financial statement has been released, and portfolios are losing funding for projects.

    Which of the following options are MOST appropriate to keep the project alive and on schedule? (Choose two.)

    Show answer details

    Correct answer: B, C

    B,C

    B,C

  8. 8

    Which of the following describes the difference between an acquisition and outsourcing?

    Show answer details

    Correct answer: A

    A

  9. 9

    Team members in a projectized organization are released at the end of a project and placed on the “bench”.

    Which of the following should the benched team members do NEXT?

    Show answer details

    Correct answer: A

    A

  10. 10

    Which of the following features describe a projectized organization? (Choose two.)

    Show answer details

    Correct answer: B, E

    B,E

    B,E