Skip to content

C-ACT-2403 SAP Certified Associate Project Manager Practice Questions

Prepare for C-ACT-2403 with more than an answer.

236 questions in the full set20 sample questionsUpdated Oct 18, 2025
Exam fee
$1308 USD
Level
Associate
Valid for
Certification does not expire
Domains covered on the exam 7
  1. Introduction to SAP Activate15%
  2. Agile Project Planning15%
  3. Agile Project Delivery15%
  4. Workstreams Overview15%
  5. SAP Activate Methodology Foundation and Tools10%
  6. Transition Paths - Cloud Implementations10%
  7. Transition Paths - On-Premise Implementations10%
  1. 1

    During sprint planning, the development team estimates they have a capacity of 40 story points for the upcoming sprint. The product owner has prioritized user stories totaling 60 story points. What is the correct agile approach?

    Show answer details

    Correct answer: B

    A core principle of Scrum is maintaining a sustainable pace. During sprint planning, the development team has the final say on how much work they can pull from the product backlog based on their calculated capacity (velocity). They should only commit to the amount of work they are confident they can complete, which in this case is 40 story points, selecting items in order of priority.

  2. 2

    A project is in the Realize phase. The configuration for a specific process has been completed in the development system. According to the SAP Activate workstream sequence, what is the immediate next step for this configuration object before it is promoted to the quality assurance system?

    Show answer details

    Correct answer: C

    In the Realize phase, after a configuration or development object (WRICEF) is built, the immediate next step is for the consultant or developer to perform unit testing. This is done within the development system to verify that the object functions correctly in isolation before it is transported to the quality assurance system for more comprehensive integration testing.

  3. 3

    Which phase in the SAP Activate methodology concludes with the Quality Gate (Q-Gate) that confirms the solution is ready for deployment and the business is prepared for cutover?

    Show answer details

    Correct answer: B

    The Realize phase concludes with a crucial Quality Gate. The exit criteria for this Q-Gate include the successful completion of all testing cycles (including UAT), finalization of the cutover plan, and confirmation that end-users are trained and the organization is ready for the transition. Passing this gate provides the formal approval to proceed to the Deploy phase.

  4. 4

    A project manager is overseeing a system conversion project. The technical team plans to use the Software Update Manager (SUM) tool with the Database Migration Option (DMO). Which activities does this combined approach perform? Select all that apply.

    Show answer details

    Correct answer: A, B, D

    The SUM tool is responsible for the software update, which includes updating the application code to the target S/4HANA version.

    The Database Migration Option (DMO) is a feature of SUM that combines the system update with the database migration to SAP HANA in a single procedure, reducing overall downtime.

    As part of the conversion process managed by SUM, the tool handles the automated data conversion steps required to move from the old ECC data models (e.g., separate FI/CO tables) to the new S/4HANA Universal Journal (ACDOCA).

  5. 5

    The 'Definition of Done' (DoD) is a critical artifact in Scrum. What is its primary purpose within an SAP Activate project?

    Show answer details

    Correct answer: C

    The Definition of Done is a checklist of activities (e.g., code complete, unit tested, documentation updated, peer reviewed) that must be completed for a product backlog item to be considered potentially shippable. It ensures consistent quality and transparency, preventing partially completed work from being declared 'done'.

  6. 6

    A global manufacturing company is embarking on a large-scale SAP S/4HANA transformation program involving multiple teams working on different functional areas simultaneously. To manage dependencies and align all teams on a common cadence, which agile framework, often used in conjunction with SAP Activate, is most suitable?

    Show answer details

    Correct answer: C

    The Scaled Agile Framework (SAFe) is specifically designed for large-scale, complex programs like this. It introduces concepts like the Agile Release Train (ART), which aligns multiple agile teams to a common mission, and Program Increment (PI) Planning, a ceremony for synchronized, cadence-based planning across all teams. This makes it ideal for managing the complexities of a large SAP transformation.

  7. 7

    A project team needs to understand the dependencies between the 'Data Management' and 'Testing' workstreams during the Realize phase. Which diagram best illustrates the required sequence of activities?

    gantt title Workstream Dependencies in Realize Phase dateFormat YYYY-MM-DD section Data Management Load Test Cycle 1 Data :done, d1, 2024-01-01, 3d Load Test Cycle 2 Data : d2, after t1, 3d Load UAT Data : d3, after t2, 3d section Testing Integration Test Cycle 1 :active, t1, after d1, 7d Integration Test Cycle 2 : t2, after d2, 7d User Acceptance Testing : t3, after d3, 10d

    Based on the diagram and SAP Activate principles, which statement is correct?

    Show answer details

    Correct answer: C

    The Gantt chart clearly shows a finish-to-start dependency. 'Integration Test Cycle 1' (t1) can only start after 'Load Test Cycle 1 Data' (d1) is complete. Similarly, 'Integration Test Cycle 2' (t2) depends on 'Load Test Cycle 2 Data' (d2), and UAT (t3) depends on 'Load UAT Data' (d3). This reflects the logical sequence in a project: data must be available in the target system before it can be used for testing.

  8. 8

    A project manager is leading a system conversion from SAP ECC 6.0 EHP8 to SAP S/4HANA 2023 On-Premise. The initial analysis from the SAP Readiness Check tool identifies over 5,000 simplification items. Which phase of the SAP Activate methodology is primarily dedicated to analyzing these items in detail and determining their disposition (e.g., adopt, replace, retire)?

    Show answer details

    Correct answer: C

    The Explore phase is where the project team conducts Fit-to-Standard analysis and detailed gap identification. For a system conversion, this includes a thorough review of the simplification items identified by the SAP Readiness Check. During this phase, workshops are held to decide how to handle each item, which is crucial for defining the scope of the Realize phase.

  9. 9

    During the setup of a new SAP S/4HANA Cloud implementation project, the project manager needs to ensure all project tasks, deliverables, and timelines are aligned with SAP's recommended practices for a cloud deployment. Which SAP tool provides pre-configured, phase-based roadmaps with accelerators and deliverable templates specifically for this purpose?

    Show answer details

    Correct answer: D

    The SAP Roadmap Viewer is the central tool for accessing SAP Activate implementation roadmaps. It provides a detailed, hierarchical view of phases, deliverables, tasks, and accelerators. Project managers use it to build their project plan and ensure alignment with SAP's standard methodology for the specific solution being implemented, such as SAP S/4HANA Cloud.

  10. 10

    A company is planning a Selective Data Transition to SAP S/4HANA. They want to consolidate three legacy SAP ECC systems into a single S/4HANA client while migrating only the last three years of transactional data. Which SAP tool or service is specifically designed to manage this type of complex migration scenario?

    Show answer details

    Correct answer: C

    SAP Landscape Transformation (LT) Replication Server, often leveraged by specialized SAP services and partners, is the primary toolset for complex scenarios like Selective Data Transition. It allows for system consolidation, carve-outs, and migrating specific slices of data (like a time slice) from one or more source systems to a new target system, which perfectly matches the described scenario.

Create an account to continue.