A project team conducted a risk analysis and created the following matrix:
Impact Probability | Low (1) | Med (3) | High (5) ----------------------------------------- High (5) | Risk C | Risk A | Risk D Med (3) | | Risk E | Low (1) | Risk B | |They calculate the risk priority by multiplying the probability and impact scores. Which risk should be the highest priority for the team to mitigate?
Show answer details
Correct answer: C
To determine the priority, calculate the risk score for each item: Risk A = 5 (Prob) * 3 (Impact) = 15. Risk B = 1 * 1 = 1. Risk C = 5 * 1 = 5. Risk D = 5 (Prob) * 5 (Impact) = 25. Risk E = 3 * 3 = 9. Risk D has the highest score (25) and therefore represents the highest priority for mitigation.
- 2
Which TWO project planning tools are best suited for visualizing task dependencies and identifying the sequence of activities that determines the total project duration? (Select TWO)
Show answer details
Correct answer: B, D
CPM is a technique specifically used to identify the sequence of critical tasks and determine the minimum time to complete a project. It explicitly maps out task dependencies.
A PERT (Program Evaluation and Review Technique) chart is similar to a CPM diagram in that it visualizes task dependencies and helps identify the critical path. It is often used when task durations are uncertain, using optimistic, pessimistic, and most likely time estimates.
- 3
A team is measuring the time it takes to complete a customer support ticket. The data is continuous. They want to check if the measurement system is reliable, specifically how much variation is contributed by the different support agents (appraisers) and the consistency of a single agent's measurements. Which study should they conduct?
Show answer details
Correct answer: C
A GR&R study is the standard MSA tool for continuous data. It specifically quantifies the variation from two sources: Repeatability (the variation from one appraiser measuring the same item multiple times) and Reproducibility (the variation between different appraisers measuring the same item). This directly addresses the team's needs.
- 4
A process has an upper specification limit (USL) of 50 units and a lower specification limit (LSL) of 40 units. A process capability study finds that the process mean is 48 units and the standard deviation is 1.5 units. What is the Cpk for this process?
Show answer details
Correct answer: A
Cpk is the lesser of Cpu and Cpl. Cpu = (USL - Mean) / (3 * StdDev) = (50 - 48) / (3 * 1.5) = 2 / 4.5 = 0.44. Cpl = (Mean - LSL) / (3 * StdDev) = (48 - 40) / (3 * 1.5) = 8 / 4.5 = 1.78. The Cpk is the minimum of {0.44, 1.78}, which is 0.44. This indicates the process is not capable and is producing defects primarily against the upper specification limit.
- 5
A Green Belt needs to create a graphical representation of a dataset to check for normality. Which of the following graphical tools is specifically designed to plot observed data against the values expected from a standard normal distribution?
Show answer details
Correct answer: C
A normal probability plot is the most precise tool for assessing normality. It plots the sorted data values against their expected z-scores from a normal distribution. If the data is normal, the points will form a nearly straight line. Deviations from the line indicate skewness, kurtosis, or other departures from normality.
- 6
A financial services company is launching a new investment product. The project team has chosen a Design for Six Sigma (DFSS) methodology. They are currently in the process of translating broad customer needs into specific, technical design requirements and identifying potential failure modes for the product's online portal. Which DFSS methodology is most likely being used, and what is the key activity in this phase?
Show answer details
Correct answer: B
The scenario describes activities in the 'Measure' and 'Analyze' phases of DMADV. In 'Measure', customer needs (CTQs) are identified and translated into measurable design specifications. In 'Analyze', the team analyzes design options and identifies potential failure modes, often using FMEA. IDOV's 'Design' phase focuses more on developing detailed designs after requirements are set, and 'Optimize' involves refining it, often with advanced tools like simulation.
- 7
A project team at a logistics company created the following value stream map for their package sorting process. They identified several areas of waste.
[Receive Pkg] -> [Wait: 2 hrs] -> [Scan In] -> [Wait: 4 hrs] -> [Sort] -> [Inspect: 10% of pkgs] -> [Wait: 3 hrs] -> [Load Truck] VA: 5 min NVA: 2 hrs VA: 2 min NVA: 4 hrs VA: 10 min NVA: 15 min NVA: 3 hrs VA: 20 minBased on the map, which Lean concept should the team prioritize to address the most significant form of waste shown?
Show answer details
Correct answer: C
The value stream map clearly shows that the overwhelming majority of the process time is non-value-added (NVA) waiting time (2 + 4 + 3 = 9 hours). The core Lean principle of Flow aims to minimize or eliminate such interruptions and delays, creating a smooth, continuous movement of work. Addressing the waiting times (a form of waste) is the highest priority identified in this map.
- 8
A hospital's Six Sigma steering committee is evaluating potential projects. Project A aims to reduce patient admission time by 10%. Project B aims to implement a new, experimental surgical robot. Project C aims to redesign the employee cafeteria menu. According to Six Sigma principles, which project is the most suitable and why?
Show answer details
Correct answer: C
Effective Six Sigma projects are tightly linked to organizational goals and key business drivers. Reducing patient admission time directly impacts patient satisfaction, operational efficiency, and potentially patient outcomes, which are core metrics for a hospital. The goal is specific and measurable. Project B is a research/capital project, not a process improvement project, and Project C is not linked to a key business driver.
- 9
True or False: The primary purpose of calculating the Risk Priority Number (RPN) in a Failure Mode and Effects Analysis (FMEA) is to satisfy regulatory compliance requirements for process documentation.
Show answer details
Correct answer: B
The primary purpose of the RPN (Severity x Occurrence x Detection) is to prioritize risks and focus improvement efforts on the potential failure modes that pose the greatest risk to the process or product. While an FMEA may be part of regulatory documentation, its core function is risk prioritization, not compliance fulfillment.
- 10
A key difference between a Design FMEA (DFMEA) and a Process FMEA (PFMEA) is their primary focus. A DFMEA is concerned with failures related to _______, while a PFMEA is concerned with failures related to _______.
Show answer details
Correct answer: B
A Design FMEA focuses on failures that can occur due to the design of the product itself, such as incorrect material choice, wrong tolerances, or software bugs that affect functionality. A Process FMEA focuses on failures that can occur during the manufacturing or delivery of the product/service, such as incorrect machine setup, operator error, or shipping damage, which are all related to process execution.